Readiness: 55,9%
PIC works (excavation development) - 100%
Pile foundation works - 100%
Installation of foundation drainage - 100%
Installation of foundation slab - 100%
Installation of foundation slab - 100%
Installation of monolithic frame below the +0,000 level - 100%
Installation of monolithic frame above +0,000 - 100%
Installation of masonry - 75%
Roofing installation - 100%
Installation of translucent structures (windows, stained glass windows) - 12%
Installation of internal engineering communications - 44%
Installation of external engineering communications - 22%
Installation of EE networks - 8%
Installation of CC networks - 25%
Pre-finishing of flats and common use areas - 25%
Finishing of flats and common use areas - 0%
Arrangement of enclosing structures (doors) - 0%