Readiness: 44%
PIC works (excavation development) - 100%
Pile foundation works - 100%
Installation of foundation drainage - 100%
Installation of foundation slab - 100%
Installation of foundation slab - 100%
Installation of monolithic frame below the +0,000 level - 100%
Installation of monolithic frame above +0,000 - 90%
Installation of masonry - 65%
Roofing installation - 25%
Installation of translucent structures (windows, stained glass windows) - 10%
Installation of internal engineering communications - 38%
Installation of external engineering communications - 0%
Installation of EE networks - 0%
Installation of CC networks - 0%
Pre-finishing of flats and common use areas - 0%
Finishing of flats and common use areas - 0%
Arrangement of enclosing structures (doors) - 0%